BAT – Vinataba

Manufacturing retrofit

BAT – Vinataba

A turnkey chiller plant modernization delivered while the Dong Nai factory remained in production.

Client
BAT – Vinataba
Location
Dong Nai, Vietnam
Period
18 Oct – 20 Dec 2015
Capacity
520 RT
Scope
Turnkey plant retrofit

Results

The outcomes in context.

Energy saving per day
≈3,100 kWh
Energy saving per year
≈1,131,500 kWh
Chiller energy saving
≈50%

Project story

From the operating brief to the handover.

The challenge

Understand what needed to change.

The plant’s existing YORK chillers operated at approximately COP 3.0. Chilled-water pumps had no VFD, and the reference records approximately 2,552,000 kWh/year of chiller plant electricity use. APC had to replace two YORK chillers without interrupting production.

Our solution

Coordinate the plant as one system.

APC supplied a 520 RT SMARDT oil-free magnetic-bearing chiller with four compressors, iCPECS control of the chilled-water pumps, condenser-water pumps and cooling towers, pump VFDs, piping and field instruments.

The result

Review the documented outcome.

The reference reports approximately 3,100 kWh/day and 1,131,500 kWh/year of energy savings, with roughly 50% chiller savings against the previous system. Maintenance costs were reduced and selected removed components were retained as spares.

Before & after

What changed in the plant.

Existing system

Chillers
2 YORK units selected for replacement; COP approximately 3.0
Chilled-water pumps
No VFD
Annual plant electricity
Approximately 2,552,000 kWh/year

APC solution

Chiller
SMARDT 520 RT, 4 compressors, oil-free magnetic bearings
Pumps and towers
iCPECS coordination; VFD on pumps
Annual energy saving
Approximately 1,131,500 kWh/year

Scope of supply

A clear delivery scope.

  • Site survey and engineering consultancy
  • Custom design for energy optimization
  • Proposal and energy-saving estimate
  • Installation and supervision
  • Project management
  • Testing, commissioning and performance verification
  • Operator training and documentation
  • Yearly maintenance, spare parts and troubleshooting service

Work performed

18 Oct – 20 Dec 2015

  1. 01Remove the two selected YORK chillers within a 24-hour window
  2. 02Lift the SMARDT unit into position using a 50-ton crane
  3. 03Connect chiller power and the iCPECS control panel
  4. 04Install pump VFDs, piping and field instruments
  5. 05Commission and verify the operating performance
  6. 06Train chiller and iCPECS operators

Key equipment

The equipment behind the scope.

SMARDT oil-free water-cooled chiller

520 RT, approximately 1,828 kWr; 4 compressors

View equipment

iCPECS

Chilled-water pumps, condenser-water pumps and cooling towers

Pump VFDs and field instruments

Piping, power connections and measurement points

Commissioning data

Recorded under real test conditions.

The following part-load ranges describe this installation’s commissioning tests. They are not rated performance guarantees for other projects.

LoadCapacity (kWr)Input (kWe)COP
59–63% load920–995120–1337.4–8.0
43–45% load680–71774–798.7–9.6

Turnkey project

Ready to plan the next one?

Talk to APC